Gallows Reach workparty report – Autumn 2026

By early July we’d pretty much completed our activity at the Wharf end and started to work our way off site, tidying up as we went; casting more concrete base slabs and completing the blue bricks on the reinforcing wall.

Summer had also arrived, bringing several heatwaves to contend with. We took the opportunity to fix the Heras fencing to the wall, allowing us to widen the towpath and top it off with sand blinding, so it was easier to walk on. There was also some shade under the trees, important when afternoon temperatures rose to over 30oC.

By early August the second headwall was finished and the concrete pads were complete up to its base.

So it was time to open up the big pipe, insert a blanking bung and divert the water through the 300mm plastic pipe that had been previously installed by the contractors. We had a few hours after we fitted the bung to remove the concrete pipe and run the plastic one back into it.

Changeover day went really smoothly and by the next morning we’d started to remove further sections of big pipe. We had even prepared the first pad from where the pipe had been removed. The team left site that Wednesday afternoon, pleased with progress and ready to cast the next pad the following Tuesday.

Unfortunately, that Thursday saw the abrupt end of the dry spell with Lichfield having the highest rainfall in the UK.

The 300mm plastic bypass pipe had less than 20% of the big pipe’s capacity so couldn’t cope with the storm surge. Neither could the 85-metre-long attenuation ‘tank’ (i.e. the first section of canal), causing the bund to overtop. This flooded the entire work site, submerging most of our plant.

The team returned the following Tuesday, feeling a bit depressed. We spent the day pumping out the remaining water and building a more robust Mk2 bund using dumpy bags with its sides supported by scaffolding tube.

It was the following week before we could progress another base, but complete it we did, even if it was two weeks later than planned.

An inspection chamber originally prevented the contractor from completing c6m of reinforcing wall. Once the pipe and chamber was decommissioned, it could all be dug out together with 14 sections of pipe. We still need to reinforce that section of original towpath wall.

The summer period has now passed and it’s started routinely raining again, so we’re taking no chances this winter. We’ve created a secondary bund at around 120m in the hope that, if storm water breeches the first bund, the second one should prevent our work site from flooding.

And finally – what’s going on here?

All will be revealed in the next edition.

Mike Babb
Workparty volunteer