WORKING PARTY BLOGS

Darnford Moors

November

A simple little task, Won't take more than a few days or a week or so. That 's what I thought when we started work just the other side of the lift bridge by the Darnford Moors Golf Club. How wrong can I be? How can a task as simple as pulling the shuttering into shape and securing it escalate it to a major project ?
This 'simple task' mushroomed into one that is going to employ our volunteers for many a month or more.

Read More

Tamworth Rd./ Darnford

October

As predicted in my September Blog, the finishing touches to the area between the narrows and the A51 were successfully completed
The area is now finished and all we need is a deluge of rain to get some water in it. 

Read More

Fosseway Heath

October

The Trust volunteers activity over the last couple of weeks has been creating a great deal of interest with the regular dog walkers and users of the Fosseway Heath section of the Lichfield Canal.

Read More

Tamworth Road

September

Nearly there, so nearly there, and the work being undertaken beyond the narrows and Tamworth Road will be finished. The only holdup now could be horrendous weather, but that is not forecast. 

Read More

Summerhill

August

The last four weeks have been a challenge as the main holiday period and school holidays have restricted the number of volunteers. The grandparents amongst the group have been on standby for kids thought the six weeks. 

Read More

Tamworth Road

August

Following on from my July Work Party Blog, the work down between the A51 and the narrows of pound 27 has progressed steadily. All the concreting of the canal base has been completed. The only concreting left to be done down there is the back filling between the wall...


Read More

Summerhill

July

It's hard to believe that it has been over two months (6th June) since Peter Buck marked out Lock 9A and work began. There has been steady progress with the work and stringent safety procedures have been put in place every step of the way.



Read More

Tamworth Road

July

The gang have worked tirelessly down between the narrows and the A51. During this month we have seen great strides towards completing the concreting down there. As before, as mentioned in the June blog, we again took delivery of another couple of loads of concrete from a 'mix it on site' source in July.



Read More

Summerhill

June 2017

This month has seen some amazing work done at the Summerhill site. Work on the basic towpath was completed as far as the new steps "Dora's Descent" that climb up the embankment to the Boat Inn. 
 



Read More

Tamworth Road

May 9th - May 31st.

You can never be sure when the weather is going to catch you out. Since my last blog the team had been making great progress in Pound 25. 

Read More

Summerhill

May 2017

This month has seen dramatic improvements to the Summerhill stretch of canal. Work began with us identifying the line of the old towpath at the Boat Inn end and the embankment was scraped down and the hedge was trimmed.
 
  
 
 

Read More

Tamworth Road

April 11th to May 9th

It's a case in this blog of either being encouraged by the progress made during the recent fine weather, or down-hearted by our failure to get the big pipe removed out of pound 25.  

Also includes a Summerhill Update.




Read More

Tamworth Road

March 11th to April 10th

This last month has seen some remarkable progress down at Tamworth Road mostly  down in Pound 25. Progress on the canal beyond the narrows by the A51 has been, and still is, blighted by water in the base of the canal which refuses to dry up.
 
 
 


Read More

Tamworth Road

Feb 18th to March 10th

Although a lot of hours of work have been put in at the Tamworth Road site over this period, there is little to report in the way of progress. It is a case of ongoing work rather than goals achieved. 




Read More

Darnford Park

Feb 22nd

This Wednesday Tom Hogan brought his tree chipper to Darnford Park again and with a large enthusiastic group of our volunteers set about reducing the brash from earlier forestry clearance work to wood chips.

Read More

Tamworth Road

Jan 15th to Feb 17th

I have been on holiday for ten days at the beginning of February, getting some much needed winter sun. So this report is basically in two halves, before and during this holiday period, and I'm sorry it's late.

Read More

Tamworth Road

Jan 1st to Jan 15th

The Festive Season is now well over and drifting into the distant past. We've had a long break from working on the canal, (those of us who usually work down at Tamworth Road any way, 



Read More

December 2016

The A51 approach has become a 'no go' area, a sea of mud. However, to keep the job going we have had to do some serious 'mud wallowing'.

See also The Grounds and Green Team Autumn Report.


Read More


FOLLOW US

LICHFIELD AND HATHERTON CANALS RESTORATION TRUST

LHCRT.org.uk
Home Page
About Us
Contact Us
News Index

Registered Office: 
Island House, Moor Road
Chesham, Buckinghamshire
HP5 1WA

Registered in England
 No. 2456172

Registered Charity
No. 702429

VAT registration
No. 823 8213 41 

LHCRT is a member of the 

Inland Waterways Association

and the

Staffordshire Waterways Group


Website design by Paul Marshall

Copyright (c) Lichfield and Hatherton Canals Restoration Trust 2016